Installation of OBERMEYER spillway gates is quick and easy. For systems up to approximately 4 Meters high, the air bladders are secured to the spillway with a row of anchor bolts. For system heights above 4 meters, an embedded clamp is used to secure the gate system to the spillway. The anchor bolts may be embedded in a new spillway or may be secured in holes drilled into an existing spillway. The air supply lines which connect to each individual air bladder can be embedded or grouted into a saw slot in the spillway. Surface mounted air supply lines may also be used. A typical installation sequence is as follows:

 

 

  • Place anchor bolts
  • Install air supply lines
  • Install abutment plates, if used
  • Place air bladders over anchor bolts
  • Secure air bladders to spillway with clamp bars
  • Connect air supply lines to underside of air bladders
  • Attach steel gate panels to each air bladder
  • Attach interpanel seals
  • Attach restraining straps if used
  • Attach nappe breakers
  • Adjust and grout abutment plates or install J seals
  • Install compressor, drier and controls
  • Start up system